Figure 128. Hot-swap power supply removal
Step 4. Install the power-supply-unit filler to cover the power supply bay.
Figure 129. Power-supply-unit filler installation
After you finish
1. Install a new power supply unit to cover the power supply bay. See
“Install a hot-swap power supply
unit” on page 136
.
Important: To ensure proper cooling during normal server operation, both power supply bays must be
occupied. This means that each bay must have a power supply unit installed; or one has a power supply
unit installed and the other has a power-supply-unit filler installed.
2. If you are instructed to return the component or optional device, follow all packaging instructions, and
use any packaging materials for shipping that are supplied to you.
Install a hot-swap power supply unit
Use this information to install a hot-swap power supply unit.
About this task
The following describes the information that you must consider when installing a power supply unit:
136 ThinkSystem SR630 V4 User Guide