363-206-305 System Turnup:
NTP-013
Issue 3, June 2000 Page 3 of 4
DDM-2000 F
IBER
R
EACH
W
IDEBAND
S
HELF
DO ITEMS BELOW IN ORDER LISTED . . . . FOR DETAILS, GO TO
7. Verify that no LEDs or alarms are activated. If any LEDs or
alarms are activated, refer to Trouble Clearing: IXL-001 and
follow the appropriate trouble-clearing procedure.
8.
NOTE:
DS1 cross-connections have to be made at each shelf to
configure the transmission path for each T1 circuit being
established. Either terminating (drop) cross-connections are
made at terminating nodes and pass-through
cross-connections are made at intermediate nodes.
NOTE:
The following commands may be used to delete, enter, and
retrieve cross-connections: dlt-crs-vt1, ent-crs-vt1,
and rtrv-crs-vt1. See the "Commands and Reports"
section of this manual for a description of commands. See
"Cross- Connection Provisioning" in the "Administration and
Provisioning" section of this manual for more information on
cross-connection provisioning.
Determine the necessary cross-connections for each node from
the work order or circuit order.
DLP-526
DLP-528
9. Make necessary VT1.5/STS1 cross-connections at each node in
the network.
A. Single/Dual Homed OC-3 or OC-12/OC-1 Configuration
B. Stand Alone OC-3/OC-1 Ring Configuration
DLP-530C. Single/Dual OC-48 or OC-192/OC-3 or OC-12 Ring
Configuration
DLP-535D. Single/Dual OC-12/OC-3 Ring Configuration