Rigging work
12.7 Rigging/unrigging the counterweight
Operating manual GMK 6400 3 112 993 en 12 - 63
12.07.2013
5. If necessary, lift and set down further counterweight sections individu-
ally, one after another;
à p. 12 - 67.
6. Secure the counterweight sections;
à p. 12 - 79.
7. Slew the superstructure into the
0° to the rear position and lock;
à Braking the slewing movement, p. 11 - 102,
à Locking/unlocking the superstructure, p. 11 - 13.
8. Establish the hydraulic and electrical connections between the 15 t base
plate and the turntable;
à Establishing/disconnecting the hydraulic connection, p. 12 - 100,
à Making/breaking the electrical connection, p. 12 - 101.
9. Connect the hand-held control to the rear right of the turntable and start
the crane engine;
à Starting/turning off the engine with the hand-held control, p. 12 - 23.