UNIVERGE SV8100 Issue 4.1
System Hardware Manual 4 - 73
5.2.2 Installation
To install the PZ-4COTE
:
1. Four plastic spacers are included with the COIDB. Install the
plastic spacers on the CD-4COTA or CD-LTA blade. Make sure
to attach the spacers so that they extend out on the side of the
daughter board which has the CN1 connector.
2. Position the PZ-4COTE CN1 connector over the CN4
connector on the CD-4COTA or CD-LTA. Press the blades
together, ensuring the plastic spacers lock in place.
3. Install the PZ-4COTE blade (refer to
Figure 4-25 Installing the
PZ-4COTE Daughter Board on page 4-71
).
5.2.3 Connectors
Table 4-37 PZ-4COTE RJ-61 Cable Connector Pin-Outs on page
4-73 shows the pin-outs for the RJ-61 connector. Refer to Figure
4-25 Installing the PZ-4COTE Daughter Board on page 4-71 for an
illustration showing the location of the connectors on the PZ-4COTE
blades.
Table 4-37 PZ-4COTE RJ-61 Cable Connector Pin-Outs
RJ-61 Cable Connector
CN2, Trunks – Connecting to COIU Blade
The CN2 connector is polarity sensitive (tip-to-tip, ring-to-ring).
Pin No. Connection
1 Circuit 8 – Tip
2 Circuit 7 – Tip
3 Circuit 6 – Tip
4 Circuit 5 – Ring
5 Circuit 5 – Tip
6 Circuit 6 – Ring
7 Circuit 7 – Ring
8 Circuit 8 – Ring