Mounting and Commissioning
This chapter is intended for experienced commissioning staff. He must be familiar with the commissioning of
protection and control systems, the management of power systems and the safety rules and regulations.
Hardware adjustments to the power system data might be necessary. The primary tests require the protected
object (line, transformer, etc.) to carry load.
3.1 Mounting and Connections 366
3.2 Checking Connections 412
3.3 Commissioning 417
3.4 Final Preparation of the Device 436
3
SIPROTEC 4, 7SJ62/64, Manual 365
C53000-G1140-C207-8, Edition 08.2016