Checklists
Checklists for Installation Technicians
Install and Cable Cabinet Checklist
This checklist highlights the high-level tasks for installing and cabling the cabinet to
physically connect and access the Definity One or Avaya IP600 system.
Installation Tasks For More Information
 For IP600, verify that all site requirements are
met.
See ‘‘Site Requirements’’ on
page 1-3.
 Confirm that customer’s order includes all
equipment needed.
For IP600 see ‘‘Check
customer’s order’’ on page 1-4
For Definity One see ‘‘Check
customer’s order’’ on page
1-51.
 Correct shipping errors.
~ Return defective and over-shipped
equipment.
Returned: ___________
Date: ______________
~ Direct short-shipped reports to nearest
MSL.
Report #:___________
Sent to: ___________
For IP600 see ‘‘Correct
shipping errors’’ on page 1-4
For Definity One see ‘‘Correct
shipping errors’’ on page 1-51.
 Unpack and inspect equipment using lifting
precautions.
For IP600 see ‘‘Unpack and
inspect’’ on page 1-5
For Definity One see ‘‘Unpack
and inspect’’ on page 1-51.
 For IP600, determine which equipment is
required and which is optional.
See ‘‘Comcodes for equipment
used with Avaya IP600’’ on
page 1-8.