3. Series 8 I/O Installation and Upgrades
3.3. Installing the Series 8 IOTA on the Panel
44 Series 8 I/O User's Guide R500
Honeywell April 2017
Step
Action
8X-TDODB1
12 inch
6
8X-TPOXA1
6 inch
4
When mounting either the 9 or 12 inch IOTA board, it is recommended to
secure the three mounting screws on one side (either left or right) and then
secure the other side.
NOTE: Securing the four corner screws and the two middle screws may
cause bowing of the board and impact the alignment of the IOTA board to the
carrier holes and is not recommended.