3. Series 8 I/O Installation and Upgrades
3.3. Installing the Series 8 IOTA on the Panel
R500 Series 8 I/O User's Guide 43
April 2017 Honeywell
3.3 Installing the Series 8 IOTA on the Panel
Prerequisites
Panel for mounting IOTA is installed in a cabinet or desired mounting location.
Power supply is installed.
All wiring and pre-fabricated cables are available and labeled as applicable.
Ensure all power is turned off at the installation location.
You have the mounting hardware supplied with the components.
Considerations
You can use a redundant IOTA to support a non-redundant Series 8 IOM application.
Ensure to install the non-redundant Series 8 IOM in the upper IOM location on the
IOTA.
Ensure the enclosure is connected to a protective earth ground using #8 AWG solid
copper wire.
Mounting the IOTA
Select desired mounting location on carrier and align mounting holes in
IOTA with screw-hole locations on the carrier. Ensure component side of
IOTA is facing up.