● The equipment room should have good heat insulation, and the walls and
oor should be protected against moisture.
● Take care to prevent the components and cables from damage.
● Check that the area, height, and ground bearing capacity of the installation
position meet requirements.
● To ensure good ventilation, do not place the indoor unit in the corner of a
room or at the end of a long-and-narrow room.
● During the NetCol5000-A operation, all doors and windows of the equipment
room should be closed to reduce the additional load of the NetCol5000-A.
● Take appropriate thermal insulation and antifreeze measures for outdoor
water pipes to avoid poor drainage and
insucient water supply caused by
freezing.
Figure 3-6 Maintenance space requirements (unit: mm)
(1) NetCol5000-A
(2) Equipment
3.1.4 Precautions
Before installing the smart cooling product, read this section carefully and perform
installation by strictly following the guidance in this section.
Figure 3-7 shows the structural
specications of the device.
NetCol5000-A025 In-row Air Cooled Smart Cooling
Product
User Manual (300 mm Width) 3 Installation Guide
Issue 15 (2020-12-10) Copyright © Huawei Technologies Co., Ltd. 39