Rigging work
12.1 Rigging work checklists for crane operation with the main boom
12 - 4 3 112 993 en Operating manual GMK 6400
12.07.2013
16. Install the lifting limit switch; Ã p. 12 - 126
17. Install anemometer, air traffic control light and camera on main boom;
à Anemometer and air traffic control light, p. 12 - 132,
à Camera on main boom, p. 12 - 137.
18. Perform all the required checks prior to crane operation;
à CHECKLIST: Checks before operating the crane, p. 11 - 1
19. Enter the current rigging mode on the RCL;
à p. 11 - 23
20. With the RCL adjusted accordingly, rig the counterweight combination
required for the operation according to the
Lifting capacity table;
à CHECKLIST: Counterweight, rigging, p. 12 - 62
21. If required, assemble the auxiliary hoist;
à CHECKLIST: Mounting the
auxiliary hoist
, p. 12 - 94
22. Enter the current rigging mode with the newly rigged counterweight
version on the RCL;
à p. 11 - 23