Install a Ground Cable (Optional)
Install a Ground Cable (Optional)
The system power distribution units (PDUs) achieve earth ground through their power cords.
For additional grounding, attach a chassis earth ground cable to the system. The additional
ground point enables electrical current leakage to dissipate more efficiently.
Caution - Do not install a ground cable until you confirm that there is proper PDU receptacle
grounding. The PDU power input lead cords and the ground cable must reference a common
earth ground.
Note - A grounding cable is not shipped with the system.
1.
Ensure that the installation site has properly grounded the power source in the
data center.
An earth ground is required. See “Grounding Requirements” on page 100
2.
Ensure that all grounding points, such as raised floors and power receptacles,
reference the facilities ground.
3.
Ensure that direct, metal-to-metal contact is made for this installation.
The ground cable attachment area might have a painted or coated surface that must be removed
to ensure solid contact.
4.
Attach the ground cable to one of the attachment points located at the bottom
rear of the system frame.
124 Oracle SuperCluster T5-8 Owner's Guide • May 2016

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Oracle SuperCluster T5-8 and is the answer not in the manual?

Oracle SuperCluster T5-8 Specifications

General IconGeneral
BrandOracle
ModelSuperCluster T5-8
CategoryServer
LanguageEnglish

Related product manuals