Preparing for Installation
Related Information
■
“Environmental Requirements” on page 293
■
“Perforated Floor Tiles” on page 296
Perforated Floor Tiles
If you install the server on a raised floor, use perforated tiles in front of the rack to supply cold
air to the system. Each tile should support an airflow of approximately 400 CFM.
Perforated tiles can be arranged in any order in front of the rack, as long as cold air from the
tiles can flow into the rack.
The following is the recommended number of floor tiles:
TABLE 68
Perforated Floor Tile Requirements
Rack Number of Tiles
Full rack 4
Half rack 3
Quarter rack 2
Related Information
■
“Heat Dissipation and Airflow Requirements” on page 294
■
“Environmental Requirements” on page 293
Preparing the Unloading Route and Unpacking
Area
■
“Shipping Package Dimensions” on page 297
■
“Loading Dock and Receiving Area Requirements” on page 111
■
“Access Route Guidelines” on page 112
■
“Unpacking Area” on page 113
296 Oracle SuperCluster T5-8 Owner's Guide • May 2016