Power On the System
7.
Secure the power cords in bundles.
8.
Connect the PDU power cord connectors into the facility receptacles.
Power On the System
1.
Ensure that each of the main power cords is connected.
2.
Turn on the facilities circuit breakers.
3.
Switch on power distribution unit B (PDU B) only.
Note - Do not turn on PDU A at this time.
PDU B is located on the right side of the rear of the rack. See below.
Press the ON (|) side of the toggle switches on PDU B.
130 Oracle SuperCluster T5-8 Owner's Guide • May 2016