You have formed the DC link.
Parameter
Parameter Description
p0010 Drive commissioning parameter filter (factory setting: 0)
0: Ready
2: Power unit commissioning
p3380 DC link forming, forming duration (factory setting: 0 h)
p3380 = 0 deactivates the function.
If the forming duration is changed while forming, then forming restarts with the modified
forming duration.
r3381 DC link forming, remaining time [h]
Remaining forming time.
r3382 DC link forming, status word
.00 1 signal: Forming activated
.01 1 signal: Forming active
.02 1 signal: Forming completed
.03 1 signal: Forming faulty
The inverter signals fault F07390
Form DC Link of the PM240‑2 power module
You form the DC-link capacitors by supplying a line voltage of ≤100 V to the inverter for a
defined time.
)RUPLQJIRUVWRUDJHWLPHVRI\HDUV
)RUPLQJIRUVWRUDJHWLPHVRI\HDUV
)RUPLQJIRUVWRUDJHWLPHVRIDQGPRUH\HDUV





8>9@
W>K@
Figure 5-3 Forming the DC-link capacitors
Form DC Link of other power modules
Formation of the DC link capacitors is not required for the following power modules even after
a lengthy period of storage.
PM230
PM240P‑2
PM250
Commissioning
5.3 Preparing for commissioning
Converter with the CU230P-2 Control Units
150 Operating Instructions, 09/2017, FW V4.7 SP9, A5E34257946B AE

Table of Contents

Other manuals for Siemens CU240B-2

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens CU240B-2 and is the answer not in the manual?

Siemens CU240B-2 Specifications

General IconGeneral
BrandSiemens
ModelCU240B-2
CategoryInverter
LanguageEnglish

Related product manuals