6.5 Example of a start-up concept
6-66
© Siemens AG 2006 All Rights Reserved
SINUMERIK 840D/810D Start-Up Guide (IADC) – 03/2006 Edition
1. Read in streamer tape with all the machine option files
2. Start the standard system start-up file for the basic machine in the Services/
Archive area
3. Start the PLC standard system start-up file
4. Start the machine option file (e.g. for 6 axes), NCK reset
5. Set the PLC options in the PLC dialog
When these steps are complete, the machine is in full working order with the
basic data.
Time required: 1 hour
The files for the machine options also include the size of the tool magazine
(36, 48, ..places).
N10900 $MN_INDEX_AX_LENGTH_POS_TAB_1=36
N10910 $MN_INDEX_AX_POS_TAB_1[0]=0
N10910 $MN_INDEX_AX_POS_TAB_1[1]=10
N10910 $MN_INDEX_AX_POS_TAB_1[2]=20
.........
The next initial start-up step is to scan the axes and for the mechanic or test
engineer to enter the relevant corrections (e.g. batches).
Suitable user screens may be created in the “Start-up/Machine data” area to
make this easier to use.
Example: User screens “MECHANIC” and “QSK”
Once the initial start-up is completed, all the data is saved to a standard system
start-up file. This file is then specifically for the machines that have been
brought into service and can be used later if there are any problems in restoring
the machine to its as-delivered state.
The files in the Services/Archive area for the basic machine and machine
options are no longer required and are therefore deleted.
The correction data (e.g. spindle pitch) is saved separately from the Services/
Active NCK data area to the archive.
The last step in the start-up is to stream off all the HMI data.
Sequence for
initial start-up
Size of the tool
magazine
Axis scan/
corrections
Data back-up