MODULE 3: DAILY START UP AND CHECKS
3-10 AEROSET
®
Customer Training Guide
94858-103 — July 2003
Partial Day Operation
If the System is idle for eight or more continuous hours per day on a
regular basis, the following START UP and SHUTDOWN options
should be performed daily at the times specified below.
START UP (22 min)
These options should be performed at the beginning of the daily
operation and require 22 minutes to complete:
Change Water in Bath
Wash Cuvettes
Wash Probes (and Mixers) with Water
Wash ICT™ module with ICT Reference Solution
Drain & Fill IRef Cup
Flush Water Lines
SHUTDOWN (30 min)
These options should be performed at the end of the daily operation and
require 30 minutes to complete:
Change Water in Bath
Wash Cuvettes
Wash Probes (and Mixers) with 1% Alkaline Wash Solution
Wash ICT module with ICT Cleaning Fluid and ICT Reference
Solution
Drain & Fill IRef Cup
Clear Database, All Records
NOTE: The capacity of the Database screen is 8,000
sample records or 30,000 results. The Operator will be
notified by an Error Log Message when the capacity is
depleted to 100 records. When the capacity is totally
depleted the Operator will be notified and no additional
orders will be accepted.