Figure 4-40 Fan commissioning
NO TE
The fan commissioning item is mandatory. After commissioning a component succeeds, the
system automatically performs commissioning for the next component you selected. If
commissioning fails, startup wizard ends.
Step 7 After the fan commissioning, the electric heater commissioning screen is displayed.
Use a clamp meter to measure the currents of cables electric heating and
humidication power port (X102). Enter the measured values on the screen, and
tap Submit within the time limit displayed on the screen. The controller
automatically determines whether the current of the smart cooling product is
within the normal range.
If the current is within the normal range, the system automatically performs
commissioning for the next component you selected.
If the current is beyond the normal range, the system deems that the
commissioning has failed.
NetCol5000-A025 In-row Air Cooled Smart Cooling
Product
User Manual (300 mm Width) 4 Power-On Commissioning
Issue 15 (2020-12-10) Copyright © Huawei Technologies Co., Ltd. 164