Figure 4-44 Condensate pump commissioning
Step 10 After the condensate pump commissioning, the cooling system commissioning
screen is displayed. Check whether the electric heating belt is
rmly attached to
the compressor outer wall and whether there is noticeable temperature rise by
touching the belt surface.
If yes, select Yes, and tap Submit within the time limit displayed on the
screen.
If no, select No, and tap Submit. The commissioning has failed. Locate and
repair the faults of the electric heating belt.
Figure 4-45 Cooling system commissioning
Step 11 View the commissioning result.
Figure 4-46 is displayed if component commissioning succeeds.
NetCol5000-A025 In-row Air Cooled Smart Cooling
Product
User Manual (300 mm Width) 4 Power-On Commissioning
Issue 15 (2020-12-10) Copyright © Huawei Technologies Co., Ltd. 167