CHAPTER 9
Preparation Overview
M7i Router Site Preparation Checklist on page 73
M7i Router Physical Specifications on page 74
M7i Router Rack Requirements on page 75
M7i Router Clearance Requirements for Airflow and Hardware Maintenance on page 77
M7i Router Environmental Specifications on page 78
M7i Chassis Grounding, Connection, and Cable Specifications on page 78
M7i Router Power Requirements on page 79
M7i Router Site Preparation Checklist
The checklist in Table 41 on page 73 summarizes the tasks you need to perform when
preparing a site for router installation.
Table 41: Site Preparation Checklist
NotesDatePerformed ByItem or Task
Verify that environmental factors such as
temperature and humidity do not exceed router
tolerances.
Measure distance between external power
sources and router installation site.
Select the type of rack.
Plan rack location, including required space
clearances.
Secure rack to floor and building structure.
Acquire cables and connectors.
Locate sites for connection of system
grounding.
Calculate power budget and power margin.
73Copyright © 2019, Juniper Networks, Inc.