110
6.11 Trial operation of device
Applications:
Initial start-up
Getting to know the individual control
functions
Before initial use with spraying agents
After maintenance operations
After repairs
Put the ladder in the transport position:
Fold lever (1) upwards.
Slide ladder (2) upwards.
Fold lever (1) downwards.
Snap lever (1) into a rung of the lad-
der.
Fill main container with water, see
"Filling main container, page 90".
Fold out boom, see "Folding out sprayer
boom, page 107".
Switch on pump with the PTO shaft.
Operate pump at a maximum of
550 rpm.
Switch the selection valve to the main
tank.
Switch diverting valve to spraying mode.
Switch agitator control to maximum agi-
tator action.