Operation
112
6.12.1 Prepare for distribution
Fold out sprayer boom, see "Folding out
sprayer boom, page 107".
Adjust pendulum system.
Adjust stabiliser.
Set selection valve to main tank.
Set diverting valve to spray mode.
Adjust the agitator control to the agitator
intensity according to the usage instruc-
tions of the spraying agent used.
Set the control unit according to the in-
tended distribution.
See operating instructions for SPRAYER
controller MIDI 3.0.
Switch on pump via PTO shaft.
Operate pump at a maximum of
550 rpm.
ATTENTION: In order to avoid prolon-
ged dry running of the pumps, start dis-
tributing promptly.