Commissioning
5.3 Procedure for commissioning via STARTER
Inverter chassis units
Operating Instructions, 07/2016, A5E00331449A
147
Note
Commissioning of an induction motor
The steps described below also apply to commissioning an induction motor.
When commissioning a permanent
-magnet synchronous motor, there are a few special
conditions that apply, which are detailed in a separate chapter (see "Setpoint channel and
closed
-loop control / permanent-magnet synchronous motors").
Click
Continue >
Configuring the motor Entering motor data
Figure 5-20 Configuring the motor Entering motor data
Enter the motor data (see motor rating plate).
Activate
Enter optional motor data
if necessary.
Activate
Enter optional equivalent circuit diagram data
if necessary.