60 53 362 D3472
D3472.201.10.20.02 07.2016
37
Sirona Dental A/S 3Product description
Operating Instructions DAC UNIVERSAL 3.5Presentation of the sterilization process
båÖäáëÜ
3.5
Presentation of the sterilization process
The following graphs show an overview of the process. This process
overview shows the different temperature and pressure levels over time.
Standard program
Cycle time 16
The following graph shows temperature (°C) and pressure (bar) during
the standard program, with standard settings, holding time 3 min and a
total cycle time of 16 min:
Standard program
1.A Pressure test with air
2.B Internal flush of the channels with water
3.C Oil care
4.D 3x External cold rinse
6.E 1x External warm rinse
5.F Drain chamber
7.G Back-Flush of the channels with steam
8.H Sterilization
9.I Ventilation of the chamber, open lid