7. Fieldbus Device Commissioning
7.2. Connecting Devices
R400 Experion PKS Series A Fieldbus Interface Module User's Guide 281
July 2010 Honeywell
Stage Funtion Completed
YES > Go to Stage 23 in the next section Checking Devices.
10
Be sure cable is connected to proper segment terminals on RTP
and that the RTP to CIOM-A FIM cable is connected to proper
CIOM-A FIM.
References:
Connecting RTP cable to module
Wiring
11
Connect Relcom Tester and/or Fluke Scopemeter to Link's
cable.
12
Is voltage over 9 volts?
NO > Go to Stage 13
YES > Go to Stage 14
13
Test the power supply, check that terminators are Installed
properly and check for short circuits.
Return to Stage 9
14
Does proper number of devices appear on tester?
NO > Go to Stage 16
YES > Go to Stage 15
15
Check that proper Link is downloaded and that device is
connected to proper link.
References:
Loading a CIOM-A FIM and its Links
Return to Stage 9
16
Are noise average and peak under 75 millivolts?
NO > Go to Stage 17
YES > Go to Stage 18
17
Check the integrity of all cable connections, cables and verify the
design of the link.