7. Fieldbus Device Commissioning 
7.2. Connecting Devices 
280  Experion PKS Series A Fieldbus Interface Module User's Guide   R400 
 Honeywell July 2010 
Stage Funtion Completed 
Adding CIOM-A FIM block to Project 
Loading a CIOM-A FIM and its Links 
3 
Was FIM download successful? 
NO > Go to Stage 4 
YES > Go to Stage 7 
 
4 
Is chassis and CIOM-A FIM powered?  
NO > Go to Stage 5 
YES > Go to Stage 6 
 
5 
Be sure required voltage is present at the power supply and it is 
turned On.  
Replace power supply, if required.  
Return to Stage 2. 
 
6 
Verify network connections.  
Replace FIM, if required.  
Return to Stage 2. 
 
7 
Measure and establish H1 segment baseline with Fluke 
Scopemeter and Relcom FTB-3 or equivalent equipment.
  
 
 
Go to Stage 8 in the next section Connecting Devices 
 
 
7.2 Connecting Devices 
 
Stage Funtion Completed 
8 
Connect the next device.  
References: 
Wiring
 
 
9 
Does device appear on link? 
NO > Go to Stage 10