Install an Internal Interconnect Assembly
“Servicing SP Trays” on page 243 and “Servicing SPs” on page 117.
5.
Switch on the appropriate PDU circuit breakers and power on the server.
“Returning the Server to Operation” on page 73.
6.
Verify that the fault has been cleared and the replaced component is operational.
See “Verify That a Fault Has Been Cleared” on page 54.
Related Information
■
“Remove an Internal Interconnect Assembly” on page 299
■
“Internal Interconnect Assembly Configuration” on page 298