Roche Diagnostics
Instructions for Use · Version 13.0 199
cobas b 123 POC system 7 Quality control
Configuring the QC scheduler
Configuring the QC scheduler
You can configure the QC scheduler to load manufacturer QC schemes, or create
your own QC times.
p To load the manufacturer QC scheme
1
Utilities > Configuration > Quality control > Times / intervals
2
Press the Load manufacturer QC scheme button.
A QC scheme is added into the QC scheduler.
The scheme contains the correct number of daily QC measurements needed for
the entire week. It also matches the QC scheduler with the scheduled 2P and
system calibration start times.
q
The manufacturer QC scheme is not affected by additional 2P and system calibrations
performed during the RUN-IN phase or by drift-related changes to the calibration
scheme.
However, if you change the scheduled 2P calibration interval, you have to load the
manufacturer QC scheme again.
s
p To create a new time in the QC scheduler
1
Utilities > Configuration > Quality control > Times / intervals
Figure 7-25 QC scheduler screen
2
To select the day of the week for the new time, press the and buttons at the
top of the QC scheduler panel.