In the following example, a project plan is supposed to fulfil class B require-
ments with air filters LF-AD-1, with 4 apertures and without further acces-
sory. The red arrows show the possible project plans with varying pipe
shapes and fan voltages.
1. Selection
Selection of the corresponding project planning table based on the air filter to be
used (see Chap. 5.2.2 )
Result
The project planning table has been determined
2. Selection
Selection of the number of aspiration apertures in the project planning table
Result
The achievable sensitivity class for the selected number of apertures has been
determined
3. Selection
Determinations on the sensitivity necessary to achieve the sensitivity class
Result
Determination of the detection unit and sensitivity setting
4. Selection
Selection of other pipe components ( e.g. steam trap see Chap. 5.2.2 described
components)
Result
The project planning table has been determined
5. Selection
Pipe length selection
Result
Determination of the pipe shape and necessary fan voltage