6 Installation and Maintenance
M1207026 6-5
6. Flow control tests (Section 3.4)
7. Pressure relief tests (Section 3.5)
8. Vaporizer back pressure test (Section 3.8)
9. Low-pressure leak test (Section 3.9)
10. Airway pressure gauge accuracy check (Section 5.4)
11. Alarm tests (Section 3.10)
12. Breathing system tests (Section 3.11)
13. Power failure test (Section 3.12)
14. Electrical safety tests (Section 3.13)
6.2.2 Every twenty-
four (24) months
In addition to the 12-month requirements, replace the following parts
every 24 months. All machine and ventilator parts should be replaced
before performing the checks, tests, and calibrations.
1. Replace the free breathing flapper valve.
2. Replace the free breathing valve o-ring.
M1207027 004 MANUAL−DOC, Technical Reference Manual, Technical Reference Manual for 9100c, English−default
Reproduced from the electronic master in MATRIX