26
Installing the Inverter
5.522kW (3-phase)
Power Terminal Labels and Descriptions
Terminal Labels
Name
Description
R(L1)/S(L2)/T(L3)
AC power input terminal
Mains supply AC power connections.
P2(+)/N(-)
DC link terminal
DC voltage terminals.
P1(+)/P2(+) DC reactor terminal
DC reactor wiring connection. (When you
use the DC reactor, must remove short-bar)
P2(+)/B
Brake resistor terminals
Brake resistor wiring connection.
U/V/W Motor output terminals
3-phase induction motor wiring
connections.
Note
Do not use 3 core cables to connect a remotely located motor with the inverter.
When you operating Brake resistor, the motor may vibrate under the Flux braking operation. In
this case, please turn off the Flux braking(Pr.50).
Make sure that the total cable length does not exceed 665ft (202m). For inverters < = 4.0kW
capacity, ensure that the total cable length does not exceed 165ft (50m).
Long cable runs can cause reduced motor torque in low frequency applications due to voltage
drop. Long cable runs also increase a circuits susceptibility to stray capacitance and may trigger
over-current protection devices or result in malfunction of equipment connected to the inverter.
Voltage drop is calculated by using the following formula:
Voltage Drop (V) = [
3
X cable resistance (m
Ω
/m) X cable length (m) X current(A)] / 1000