39
Installing the Inverter
Items
Check Point
Ref.
Result
Are the control cables properly wired?
p27
Are the control terminal screws tightened to their specified
torques?
p.19
Is the total cable length of all control wiring < 165ft
(100m)?
p.33
Is the total length of safety wiring < 100ft (30m)?
p.33
Miscellaneous
Are optional cards connected correctly?
-
Is there any debris left inside the inverter?
p.19
Are any cables contacting adjacent terminals, creating a
potential short circuit risk?
-
Are the control terminal connections separated from the
power terminal connections?
-
Have the capacitors been replaced if they have been in use
for > 2 years?
-
Have the fans been replaced if they have been in use for >
3 years?
-
Has a fuse been installed for the power source?
p.368
Are the connections to the motor separated from other
connections?
-
Note
STP (Shielded Twisted Pair) cable has a highly conductive, shielded screen around twisted cable pairs.
STP cables protect conductors from electromagnetic interference.
2.4 Test Run
After the post-installation checklist has been completed, follow the instructions below to test the
inverter.
1 Turn on the power supply to the inverter. Ensure that the keypad display light is on.
2 Select the command source.
3 Set a frequency reference, and then check the following:
If V1 is selected as the frequency reference source, does the reference change according to
the input voltage at VR?
If V2 is selected as the frequency reference source, is the voltage/current selector switch
(SW2) set to voltage, and does the reference change according to the input voltage?

Table of Contents