1. Open the 11.1.1
<Error behaviour – Communication – SAM 4.0>
menu.
4 0 0 m b a r 0 8 : 1 5 A M 8 0 ° C
Header
11.1.1 SAM 4.0
Menu
Send/Receive
Active line
Load signal
Load
Option Load
2. Use «Up» or «Down» to select the topmost line.
3. Press «Enter».
The setting mode is active.
4. Use «Up» or «Down» key to set the
Send/Receive
option.
5. Press «Enter».
The setting is applied.
6. Use the «Up» or «Down» keys to select the
Load signal
line.
7. Press the «DOWN» key.
8. Press «Enter».
The setting mode is active.
9. Use «Up» or «Down» to set the
Load
or
ready
option.
10. Press the «Enter» key.
The setting is applied.
Result If a communication fault occurs during the master control mode and no external load signal has
been parametrised, the blower switches to the operating state that has been set in this menu.
➤ The settings for Com-Module are carried out in the same manner.
8.11 Commissioning the machine
Checking the controller settings Section Confirmed?
➤ Language correctly set? 8.2.2
➤ Date and time correctly set? 8.2.8
➤ Display format correctly set? 8.2.10
➤ OFC/SFC: Operating mode correctly set? 8.6
Tab. 82 Check list for starting the machine
1. Check and confirm all the items in the check list before first start-up of the machine.
When power is applied to the machine the controller boots and carries out a self test.
The display and the
Controller on
LED illuminate.
The actual working pressure, the time and the airend discharge temperature are displayed in
the first line of the display.
The operating mode is mapped as a pipe and instrument diagram on the display.
8 Initial Start-up
8.11 Commissioning the machine
132
Service Manual Controller
SIGMA CONTROL 2 BLOWER ≥ 2.5.3 No.: 901700 10 E