Rigging work
12.1 Rigging work checklists for crane operation with the main boom
12 - 6 3 302 690 en Operating manual
GMK4100L-1
23.11.2017
21. Install the camera on main boom if required; Ã Cameras for crane
operation
, p. 12 - 132.
22. Fold out and adjust all mirrors for crane operation;
à p. 12 - 130.
23. Perform all the required checks prior to crane operation;
à CHECKLIST: Checks before operating the crane, p. 11 - 1.
24. Enter and confirm the current rigging mode;
à Enter rigging mode,
p. 11 - 32.
25. With the rigging mode adjusted accordingly, rig the counterweight
combination required for the operation according to
Lifting capacity
table
; Ã CHECKLIST: Rigging the counterweight, p. 12 - 76.
26. Enter the current rigging mode with the new rigged counterweight
combination at the RCL display;
à Enter rigging mode, p. 11 - 32.