EKO Energy
Procedure
1. Insert the round plug into any round socket on inverter 1.
2. Insert the other end of the cable into any round socket on inverter 2.
3. Connect the other inverters to each other in the same way.
4. Terminate the last inverter according to the inverter instructions.
Allocate communication address
Recommendation: Continuous numbering starting with 1.
Default settings on the inverter: Communication address 1.
Setting: Using the inverter operating display.
Procedure: Start according to the inverter's instructions.