1. Open the inverter as shown in the inverter’s instructions.
2. Connect terminals +T/R, -T/R and RTN of inverter 1 to the corresponding terminals on inverter 2.
3. Connect the other inverters to each other in the same way.
4. Terminate in the last inverter.
Set the DIP switch for the terminal resistor to ON.
5. Close inverters.
Allocate communication address
Recommendation: Continuous numbering from Solar-Log™, starting from 2 (not 1!).
Setting: Using the inverter operating display.
Procedure: Start according to the inverter’s instructions.
New supported models (as of firmware 4.1.2):
S (1 MPPT) and SX2 (3 MPPTs) models from TRIO-TM-50.0-400, TRIO-TM-60.0-480,
TRIO-TM-60.0-480-US,
UNO-DM-5.0-TL-PLUS
UNO-DM-6.0-TL-PLUS, UNO-DM-6.0-TL-PLUS-US
UNO-DM-3.8-TL-PLUS, UNO-DM-3.8-TL-PLUS-US
UNO-DM-4.6-TL-PLUS
UNO-DM-4.0-TL-PLUS
UNO-DM-3.3-TL-PLUS-US
UNO-DM-2.0-TL-PLUS
UNO-DM-1.2-TL-PLUS
TRIO-50.0-TL-OUTD-US-480