TITANUS MICRO·SENS
®
Pipe Design
MS_A_04-en-e Data: 01/09 4 – 1
4 Design
4.1 General
The following describes the project planning of the air sampling smoke
detection system to EN 54-20. The basic conditions are described in
Chapter 4.1. The project planning is to be conducted in accordance with
Chapter 4.2.
The limiting project planning instructions in accordance with Chapter 4.2
apply to special applications in addition to Chapter 4.3 These should be
taken into consideration at the beginning of project planning for special
projects.
Project planning options according to EN 54-20:
There are various technical solutions to be selected from, depending on
the project planning criteria. The chapters for the solutions are listed in
the following tables.
Project planning crite-
rion
Technical solution Basic Prin-
ciples
Limitations
General area monitoring Standard project
planning
Chapter 4.2 ---
Recognition of a failure at
an individual aperture
Project planning for
individual aperture
monitoring
Chapter 4.2 Chapter 4.3.1
Device protection/cabinet
monitoring
Simplified pipe project
planning
Chapter 4.2 Chapter 4.3.2
Ventilation conduits Project planning for
forced air flow
Chapter 4.2 Chapter 4.3.5

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the WAGNER TITANUS and is the answer not in the manual?

WAGNER TITANUS Specifications

General IconGeneral
Power Supply24 V DC
Operating Temperature-20°C to +60°C
Alarm OutputRelay contacts
CertificationVdS, EN 54
Humidity Range10% to 95% (non-condensing)

Related product manuals