7 Commissioning
At commissioning, the test record should generally be stored in DIAG 3.
This is required for later assessment of data such as the air flow figure,
type of adjustment (see Chapter 7.1), commissioning temperature, air
pressure and height above sea level.
7.1 Commissioning the detection unit
Before the detection unit is used, the pipe system must be installed in full,
be operational and be connected to the TITANUS MICRO·SENS
®
device
base.
Device base
TITANUS
MICRO · S E N S
®
Pipe connection
Fig. 7.1: Check whether the pipe system is correctly connected
At commissioning, the TITANUS MICRO·SENS
®
detection unit is to be
inserted in the pre-mounted device base which has been checked to
ensure it is correctly wired.
When inserting the detection unit, take note of the mechanical coding
which protects the device against twisting.