Pipe Design
MS_A_04-en-e Data: 01/09 4 – 13
4.2.3 Sensitivity and pipeline project planning
4.2.3.1 Pipeline project planning with pipe accessories
The following project planning tables for pipeline project planning can be
found in the appendix for each previously selected pipe accessory.
z Project planning without filter
z Project planning with LF-AD air filter
z Project planning with LF-AD-1 air filter
z Project planning with LF-AD-2 air filter
z Project planning with SF-400 / SF-650 air filter
An area can be monitored with more than detection points than re-
quired by the national guideline in order to improve an air sampling
smoke detection system’s detection quality. In such case, the number
of normatively required sampling points is to be used in calculating the
required sensitivity of an air sampling smoke detection system.
INSTRUCTION

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the WAGNER TITANUS and is the answer not in the manual?

WAGNER TITANUS Specifications

General IconGeneral
Power Supply24 V DC
Operating Temperature-20°C to +60°C
Alarm OutputRelay contacts
CertificationVdS, EN 54
Humidity Range10% to 95% (non-condensing)