Pipe Design TITANUS MICRO·SENS
®
4 – 14 Data: 01/09 MS_A_04-en-e
Procedure In the following example, a project plan is supposed to fulfil class B re-
quirements with air filters LF-AD-1, with 4 apertures and without further
accessory. The red arrows show the possible project plans with varying
pipe shapes and fan voltages.
Selection
Selection of the corresponding project planning table based on the air filter to be
used (see Chap. 4.2.2 )
Result
1.
The project planning table has been determined
Selection
Selection of the number of aspiration apertures in the project planning table
Result
2.
The achievable sensitivity class for the selected number of apertures has been
determined
Selection
Determinations on the sensitivity necessary to achieve the sensitivity class
Result
3.
Determination of the detection unit and sensitivity setting
Selection
Selection of other pipe components ( e.g. steam trap see Chap. 4.2.2 described
components)
Result
4.
The project planning table has been determined
Selection
Pipe length selection
Result
5.
Determination of the pipe shape and necessary fan voltage.