Install Telecommunications Cabling
Task List: Installing the Telecommunications Cabling
SI Installation and Upgrades 403
June 2004
Install Telecommunications Cabling
This section provides both information about installing the telecommunications cabling and procedures
for doing the installation.
Information about Installing the Cabling
• Provisioning Plan on page 404
• Main Distribution Frame (MDF) Hardware on page 404
• MDF Cross-Connect Fields on page 406
• Main Distribution Frame on page 408
• Main Distribution Frame Labels on page 409
• Off-Premises Circuit Protection on page 410
• Cable Installation on page 411
• Sneak Fuse Panels on page 411
• Coupled Bonding Conductor on page 415
• Installation Space Requirements on page 416 for the sneak fuse panels, the 110-type hardware,
and the Cable Slack Manager
• Station Wiring Design on page 417
• Station Circuit Distribution from Equipment Room on page 421
• Layout on page 427
• Patch Cord/Jumper Installation and Administration on page 429
Task List: Installing the Telecommunications Cabling
1 Label Control Carrier Cable on page 431
2 Connect Control Carrier Outputs Cable on page 432
3 Connect Trunk Pairs Using Concentrator Cables on page 432
4 Connect Trunk Pairs to Cabinet Using Jumper Wires To Establish 3-Pair Modularity on page 433
5 Install Cables Between Cabinet and MDF on page 435
6 Install Connector Cables Between Auxiliary Cabinet and MDF on page 436
7 Mount 110A- or 110P-type terminal blocks on the wall on page 437 or Mount 110P-type terminal
blocks on a frame on page 439
8 Install Cable Slack Managers on page 441
9 Install Sneak Fuse Panels on page 443
10 Install Coupled Bonding Conductor on page 445