Release 9si/10si/Communication Manager 1.x to Communication Manager 2.1
Task list: R9si/10si/Communication Manager 1.x to Communication Manager 2.1
46 SI Installation and Upgrades
June 2004
Check SPE
Return to Task List
1 Type status system 1 and press Return.
Check these fields for the corresponding values:
— Maj/Min alarms = 0
— Service State = in service
Return to Task List
Verify the software version
Return to Task List
1 Type list configuration software-version and press Return.
The Software Versions screen appears.
2 In the UPDATE FILE section, check the Update State field for a software patch:
— If there is a patch number, then a patch has been applied.
— If the field is none in memory, there is no software patch in system memory.
If you need to restore the system to the old software version, you must also download a patch onto
the system.
3 In the SOFTWARE VERSION section note the current software version listed in the Memory
Resident
field.
Ensure that the current software version is compatible with this software-only upgrade path.
Return to Task List
Verify system status
Return to Task List
1 Type status system 1 and press Return.
Check these fields for the corresponding values:
—In the SPE ALARMS section,
MAJOR and MINOR alarms = 0
—
Service State = in service
2 If there are alarms, take the necessary corrective actions (display alarms).
3 Type display errors and press Return.
4 Examine the Hardware Error Log and record any Error Code 18 alarm that identifies existing
busyouts. After the upgrade you will restore the busyouts as they were (Restore busyouts
).
5 For configurations with existing BX.25 links that are being retained after the upgrade, type
display communication-interface links and press Return.