G3iV4 to Avaya Communication Manager
Task List: G3iV4 to Avaya Communication Manager
SI Installation and Upgrades 87
June 2004
Run acceptance tests [from G3V4]
Return to Task List
Run any acceptance tests that are appropriate for this upgrade. The acceptance tests are listed in these 3
checklists:
Test single-carrier cabinet systems
Test multi-carrier cabinet systems
Test telephones and other equipment
For details of the tests, see
Test the System
Test Telephones and Other Equipment
Test single-carrier cabinet systems
1 Check System Status for Each Cabinet
2 Check Circuit Pack Configuration
3 Test Time Division Multiplexing Bus in Processor Port Network
4 Test Tone-Clock Boards
5 Test Expansion Interface Circuit Packs
6 Test Time Division Multiplexing Bus for Each Expansion Port Network
7 Test Tone-Clock for Each Expansion Port Network
8 Test Tone-Clock Interchange for Each Expansion Port Network
9 Test Expansion Interface Exchange for Each Expansion Port Network
10 Check Circuit Pack Configuration
11 Save Translations, if Required
Test multi-carrier cabinet systems
1 Check System Status for Each Cabinet
2 Check Circuit Pack Configuration
3 Test TDM Bus in PPN
4 Test Tone-Clock Circuit Packs
5 Test SPE Duplication Memory Shadowing Link
6 Test Duplicated Switch Processing
7 Element Interchange
8 Test Expansion Interface Circuit Packs
9 Test TDM for each EPN
10 Test Tone-Clock for each EPN
11 Test Tone-Clock Interchange for each EPN