Additional Tools and Materials Required Chapter 3
FA4800 User Manual Release 1.9.40 3-6
Additional Tools and Materials Required
The following is a list of the equipment and materials required to install FA4800 hardware.
Tools and Materials
• Crimping tool for RJ-45 (if the ODU-IDU cable is without connectors)
• Spanner/wrench 13 mm (½”)
• Drill (for wall mounting only)
• Cable ties
• Sealing material
Cables and connectors
• ODU grounding cable 12AWG
• IDU grounding cable 18AWG
• ODU-IDU cable (outdoor class, CAT-5e, 4 twisted pairs, 24AWG)
• For PoE based links: A crossed Ethernet LAN cable
• O-PoE 10AWG grounding cable if applicable
• BDU grounding cable 18AWG if applicable
Hardware Installation Sequence
The following steps are required to install the FA4800 system:
1. Mounting the ODUs, page page 3-7.
2. Mounting the external antennas (if used), page page 3-8.
3. Mounting the Lightning Protection devices (if used), page page 3-8.
4. Outdoor connections, page page 3-9.
5. Mounting the IDUs, page page 3-10.
6. Indoor connections, page page 3-13.
7. Aligning the ODUs/antennas, page page 3-14.