8-6-6-3 Swivel Release Cable Installation Procedure
1) Raise the control console to its maximum height.
2) Route the swivel release cable along its original path in the machine. The end of the cable with the
adjustable sleeve should be next to the up/down/swivel handle at the front of the unit; the other end
of the cable should be next to the vertical axis welding (accessed from the left side of the unit).
3) Working from the front of the machine, insert the cable end stopper into the through the grooved
slot on the handle assembly carefully aligning the groove on the cable with that of the groove in the
slot (refer to the detail shown in Figure 8-88 on page 8-101).
4.) Feed the swivel release cable down into the slot in the cable retaining bracket (refer to Figure 8-80
on page 8-96) and tighten the securing nut against the bracket to hold the cable firmly in position.
5.) Slide the cable retaining bracket backwards (previously moved forwards) along the chassis beam
sufficiently to regain tension on the cable. Using an M4 Allen key, tighten the two cap screws on the
bracket to hold it firmly in position - refer to Figure 8-79 on page 8-96.
NOTE: For clarification, the letters appearing in square brackets [ ] in the following step correspond to the letters
shown in Figure 8-77 on page 8-95 and Figure 8-78 on page 8-95.
6) Working from the left side of the machine, press the tensioning plate [D] downwards then slide the
other cable end stopper [E] and the cable sleeve [F] into the slot in the cable retaining bracket [B].
7) Using the Up/Down/Swivel handle, swivel the control console several times to verify its proper operation.
8) Fasten the cables to the machine with cable ties (at the original positions - see Figure 8-81 below).
9.) Return the keyboard (previously removed) as described in the Keyboard Installation Procedure on
page 8 - 27.
10.)Return the control console upper cover front section, as described in the Control Console Upper
Cover (Front) Installation Procedure on page 8 - 15.
11) Pull the gas spring cover central sleeve upwards into position carefully checking that the swivel
release cable is neatly tucked inside and is not being pinched by the sleeve; return and tighten the
three screws (refer to Figure 8-76 on page 8-94).
12) Return the control console lower cover, as described in the Control Console Lower Cover
Installation Procedure on page 8 - 18.
13) Return the control console lower cover rear, as described in the Control Console Lower Rear Cover
Installation Procedure on page 8 - 19.
Figure 8-81 Cable Fastened with Cable Ties