Install the Battery
3.
Return the server to operation.
a.
Install the server top cover.
See “Install the Server Top Cover” on page 218.
b.
Return the server to the normal rack position.
See “Return the Server to the Normal Rack Position” on page 220.
c.
Reconnect the power cords to the server power supplies, and power on the
server.
See “Reconnect Power and Data Cables” on page 222 and “Power On the
Server” on page 222.
d.
Verify that the System OK LED indicator is lit.
Note - If the service processor is configured to synchronize with a network time server using
the Network Time Protocol (NTP), the Oracle ILOM SP clock will be reset as soon as the
server is powered on and connected to the network; otherwise, proceed to the next step.
4.
If the service processor is not configured to use NTP, you must do one of the
following:
■
Reset the Oracle ILOM SP clock using the Oracle ILOM CLI or the web interface.
Refer to the Oracle Integrated Lights Out Manager (ILOM) 5.0 Documentation Library at
https://www.oracle.com/goto/ilom/docs.
■
Use the BIOS Setup Utility to reprogram the host clock.
Refer to the Oracle X8 Series Servers Administration Guide at https://www.oracle.com/
goto/x86admindiag/docs.
Related Information
■
“Remove the Battery” on page 141
144 Oracle Server X8-2L Service Manual • January 2021