Remove the Server From the Rack
Remove the Server From the Rack
Caution - The server weighs approximately 64.0 pounds (29.03 kg). Two people are required to
unmount and carry the chassis.
1.
Disconnect all the cables and power cords from the server.
2.
Remove the cable management arm (CMA).
Refer to “Remove the Cable Management Arm” in Oracle Servers X8-2 and X8-2L Installation
Guide
3.
Extend the server to the maintenance position.
See “Extend the Server to the Maintenance Position” on page 62.
4.
From the front of the server, pull the green slide-rail release tabs toward the front
of the server, and pull the server out of the rack until it is free of the rack rails [1
and 2].
A slide-rail release tab is located on each slide-rail.
5.
Set the server on a sturdy work surface.
Related Information
“Disconnect Cables From the Server” on page 61
“Extend the Server to the Maintenance Position” on page 62
“Reinstall the Server Into the Rack” on page 219
64 Oracle Server X8-2L Service Manual • January 2021

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Oracle X8-2L and is the answer not in the manual?

Oracle X8-2L Specifications

General IconGeneral
BrandOracle
ModelX8-2L
CategoryServer
LanguageEnglish

Related product manuals