Connecting and Aligning ODUs / Antennas Chapter 3
WinLink™ 1000 User Manual Release 1.9 3-15
Refer to Appendix K for connector pinouts.
¾ To connect user equipment to a PoE device:
• Connect a user switch, router or any other compatible device to the PoE
device RJ-45 port designated LAN-IN. Refer to Appendix K for connec-
tor pinouts.
Connecting and Aligning ODUs / Antennas
You perform antenna alignment using the ODU's audible tone.
The method is not suitable for the following models:
To speed up the installation time, alignment of a WinLink™ 1000 system
should be performed by two teams simultaneously, at site A and at site B.
¾ To align the ODUs using the alignment tone:
1. Verify that power is connected to the IDUs at both sites.
Provided that Site A detects the signal from Site B, the ODU starts beep-
ing 20 seconds after power up, and continues beeping until the ODUs are
aligned, and the installation is complete.
2. Verify normal operation of the IDU by the LED indications on the front
panel (see Table 3-2).
3. Direct the antenna of site B in the direction of the site A. This is simplified
if a previous site survey has been completed and azimuths are known.
4. Make an azimuth sweep of 180 degrees with the site A ODU so that the
strongest signal from site B can be detected.
5. Slowly turning the site A ODU back towards the position of Site B, listen
to the tone until the best signal is reached. See the following figure for
audible signal variations.
Note
Do not connect two LAN ports to the same network, or flooding may occur.
Model See Reference
BRS Appendix I
FCC/IC 5.4 / 5.3 GHz Appendix H
AIND Appendix G
Warning
When aligning the antennas, do not stand in front of a live antenna.