Commissioning communication NCK<->Drive
9.3 Commissioning communication NCK<->Drive completed
CNC Part 1 (NCK, PLC, drive)
96 Commissioning Manual, 11/2006, 6FC5397-2AP10-2BA0
11. Select the next axis in each case with Axis+ and continue with Step 3 for the next drive.
9.3 Commissioning communication NCK<->Drive completed
Commissioning communication NCK<->PLC completed
You have placed the following in operation:
• PLC
• SINAMICS drives
• Communication NCK-PLC
The basic commissioning is completed. Now you can move the axes.
The next chapter, "Commissioning NCK", describes the parameterization of NCK regarding