EasyManua.ls Logo

Siemens SINUMERIK 804D sl

Siemens SINUMERIK 804D sl
319 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
PLC commissioning
7.5 First commissioning of the PLC completed
CNC Part 1 (NCK, PLC, drive)
Commissioning Manual, 11/2006, 6FC5397-2AP10-2BA0
61
7.5 First commissioning of the PLC completed
First commissioning of the PLC completed
You have completed the first commissioning of the PLC.
The PLC and NCK are in the following state:
LED RUN illuminates GREEN continuously.
Status display shows a "6" with a flashing point.
⇒ PLC and NCK are in cyclic operation.
Continue with the steps for commissioning the SINAMICS drives.
You can access the HMI as follows:
Figure 7-18 PLC commissioning complete

Table of Contents

Related product manuals