Commissioning
6.3 Commissioning using the STARTER commissioning tool
SINAMICS DCP
146 Operating Instructions, 09/2019, A5E34382853K
Alternatively, the download to the target system can also be performed as follows:
Step 1
Select the menu command
Target system > Download > Project to target system
Selection in the toolbar
Note
Your project data has now been transferred to the drive unit. Presently, this data is only in
the volatile memory (RAM) of the drive unit, however, neither saved in the non
-volatile
memory (ROM) nor on an opt
ionally inserted memory card (see also "Memory card
functions
(Page 158)").
To save your project data in the ROM and on the optionally available memory
card of
your drive unit so that it is protected against power failure,
carry out the following steps.
Step 2
Select the menu command
Target system > Target system > Copy RAM to ROM
Selection in the toolbar
Note
The "Copy from RAM to ROM"
icon is only active when the drive unit is selected in the
project navigator.
Results of the preceding steps
You have generated a project for your drive unit using the STARTER offline
You have saved your project data to your PC hard drive
You have transferred your project data to the drive unit
You have saved your project data in your drive unit's FLASH memory so that it is backed
up in the event of a power failure